Appendix C – Waikato Expressway – estimated costs over time
Unit: $ millions nominal.
Estimated project cost |
Estimated construction cost |
|||||||
---|---|---|---|---|---|---|---|---|
Section |
Completed |
2002 |
2006 |
2011/12 |
2014 |
2018 |
2021 |
2022 |
Mercer | July 2006 | 74.5 |
82.0 |
- |
- |
- |
||
Longswamp and Rangiriri |
December 2020 |
33.0 |
55.7 |
117.0 |
70.0 |
96.0 |
92.0 |
92.0 |
26.0 |
26.0 |
105.0 |
131.0 |
123.0 |
123.0 |
|||
Huntly |
February 2020 |
100.0 |
200.0 |
579.0 |
470.0 |
409.0 |
383.0 |
383.0 |
Ngāruawāhia |
December 2013 |
50.0 |
200.0 |
248.0 |
190.0 |
160.0 |
166.0 |
166.0 |
Te Rapa |
December 2013 |
- |
- |
194.0 |
195.0 |
172.0 |
172.0 |
172.0 |
Hamilton |
TBC |
130.0 |
280.0 |
890.0 |
790.0 |
637.0 |
837.0 |
837.0 |
Cambridge |
December 2015 |
39.0 |
70.0 |
204.0 |
230.0 |
218.0 |
182.0 |
182.0 |
Source: | Transit NZ |
Waka Kotahi NZ Transport Authority |
Source: Principal Economics, Transit NZ, Waka Kotahi NZ Transport Authority
Note: Target completion dates are sourced from a snapshots of the Transit NZ and Waka Kotahi NZ Transport Authority websites during the years shows in Table 5. Completion have been sourced from Beehive and Waka Kotahi NZ Transport Authority media releases and project overviews. Where a range has been given for estimated project cost we have used the higher of the two values.